Figure 40-6
Example of a Gantt Chart
Goal: To develop a training curriculum for school social work interns
|
|
|
|
|
|
Time Frame |
|
|
|
|
Person |
|
January |
February |
March |
April |
|
Objective
|
|
Activity |
|
Responsible |
|
4 11 18 25 |
1 8 15 22 |
1 8 15 22 29 |
5 12 19 |
| 1. |
|
Develop course objective |
|
J. Addams |
|
|
|
|
|
| 2. |
|
Prepare outlines of three modules |
|
J. Culbert |
|
|
|
|
|
| 3. |
|
Select teaching methods |
|
E. Abbott |
|
|
|
|
|
| 4. |
|
Prepare workbooks |
|
G. Lee |
|
|
|
|
|
|
|
|